Check back often for updates on the progress of construction for the Rialto Regional Biosolids Processing Facility in Rialto, California.
With just a few months to go in 2008, the Rialto Regional Biosolids Processing Facility is now 94% complete. Construction crews have completed Phase I Mechanical Completion of the site and commissioning activities have commenced for all major areas. North American Energy Services (NAES), EnerTech’s operator for the facility, has established a permanent onsite presence and is ramping up for operation.
On October 15th the plant began initial start-up by accepting its first truckload of biosolids. The event was observed by representatives from the five municipalities currently providing biosolids to the facility.
Construction crews are now focused on equipment check-out and commissioning of all major systems.
Construction of the Rialto Regional Biosolids Processing Facility is now 80% complete, with all major equipment installed on site, including the centrifuges, reactors, and heat exchangers. The site’s main features are beginning preparation for mechanical testing and completion at the end of the summer.
Recent site accomplishments include:
With all major equipment installed on site, construction has shifted focus to finalizing details such as continued installation of electrical systems, piping, and minor instruments.
Construction continues to move along with the installation of major pieces of equipment. Some of the major milestones for February include the following:
The site is taking shape and beginning to look like a biosolids processing facility. Visit the Rialto Site Photographs page for recent photos of the site.
The Rialto Regional Biosolids Processing Facility is approaching the halfway point with respect to construction. Significant progress has been made and major equipment is now being received and installed. Major recent milestones include the following:
Construction is progressing rapidly and additional equipment is expected to be received onsite in early 2008.
After receiving the Notice to Proceed on April 1, EnerTech partners HDR and Filanc, the facility’s engineering and construction firms, began mobilizing the Rialto site for construction. EnerTech hosted a ceremonial groundbreaking on May 14, 2007 to celebrate the start of construction. The ceremony was attended by state and local officials from the State of California as well as representatives from all five of the facility’s customers.
This quarter also saw major excavation of the site’s biosolids Receiving Pit and SlurryCarb™ foundations. This work is necessary to prepare these areas for the laying of foundation.
EnerTech announced the completion of financing for the Rialto facility – the first ever commercial SlurryCarb™ venture. The transaction, valued at $160 million, was financed through equity and a combination of tax exempt and taxable bonds. Deutsche Bank, a leading global investment bank, purchased 100% of the bonds.
See Also
Read the news release describing EnerTech's groundbreaking ceremony for the Rialto Regional Biosolids Processing Facility.
Download 
![]()